“I can look at timetables going back to the 1990s and there are huge improvements for Frankston line, which goes through marginal seats, but not so much in the north and west,” he said.
Parker said Melbourne train services dropped off dramatically outside peak hours, particularly with 30-40 minute waits each evening, and on Sunday mornings as trains sat idle. He pointed out that Penrith station in Sydney’s outer west had far more frequent services than similar outer suburbs in Melbourne.
“We’re pretty well set up with infrastructure now. We just don’t use it,” he said.
“Melbourne bills itself as a livable city with all these major events. A lot of them are on weekends, and a lot of them require big numbers of people to go to temporary jobs to help run these events. But the train services have certainly not kept up.”
Transport Minister Gabrielle Williams said on Wednesday that long off-peak waits on north-west Melbourne lines would be addressed, but commuters would have to wait for a network timetable revamp for the Metro Tunnel, scheduled to open later this year.
In January, The Age reported the $15 billion tunnel’s full benefits may not be realised because related network upgrades – such as a turn-back on the Upfield line at Gowrie – had been cut to rein in the project’s ballooning budget.
On Wednesday, the Herald Sun reported up to 33 fewer trains would run each peak hour when the tunnel opens compared to what was touted in a 2016 business case.
The peak period trains planned for the Sandringham line would be halved from 16 to 8 per hour while Craigieburn services would drop from 16 to 10, the newspaper said.
In response, Williams said the Metro Tunnel timetable was still being developed and framed the nine-kilometre underground line from Kensington to South Yarra as a “foundational project” that wider network enhancements would later add to, so services would be boosted further.
Loading
“You don’t build the second storey of a house before you build the first storey,” she said.
However, the Metro Tunnel’s business case included wider network upgrades – like a turn-back and platform extension at Essendon – and declared they “need to be completed to coincide with completion of the tunnel and stations works”.
A turn-back is a section of track that allows a train to change direction without having to travel to the end of the line, so more trains can run to inner-Melbourne stations with high passenger demand.
Premier Jacinta Allan inspects a Metro Tunnel project site in March.Credit: AAP
Williams said the Metro Tunnel would improve service frequency across the network as a Sunbury-to-Dandenong line would operate via five new inner-city underground stations, freeing up capacity in the City Loop for other lines.
But the opposition spokesman for major projects, Evan Mulholland, said the failure to deliver the related network upgrades showed Labor had “neglected” the northern and western suburbs that would benefit from them.
“The Allan government cannot manage money,” Mulholland said. “This is Jacinta Allan’s signature infrastructure project, and it has turned into a monumental stuff-up that fails to provide the benefits where it’s needed.”
Start the day with a summary of the day’s most important and interesting stories, analysis and insights. Sign up for our Morning Edition newsletter.
Read the full article here